ADVERTISEMENT FOR BIDS

Sealed bids for airfield pavement rehabilitation, to be constructed for the CITY OF ROANOKE at the Roanoke Municipal Airport, in Roanoke Alabama, will be received at ROANOKE CITY HALL, 809 MAIN STREET, ROAOKE, AL 36274 until 2:30 PM, THURSDAY, MAY 20, 2021, at which time the bids shall be publicly opened and read aloud. Sealed bids submitted prior to the bid opening should be sent to ROANOKE CITY HALL, 809 MAIN STREET, RONAOKE, AL 36274, ATTN: CHRIS PARMER.

An optional Pre-Bid Conference will be held on 2:30 PM, THURSDAY, MAY 13, 2021 at the ROANOKE MUNICIPAL AIRPORT, located at 728 AIRPORT ROAD, ROANOKE, AL 36274.

The project includes but is not limited to application of ALDOT bituminous treatment (Type E), asphalt paving, patching, pavement markings and shoulder edge grading as shown on the plans and indicated in the specifications.

Digital copies of the bid documents are available at http://Planroom.GarverUSA.com for a fee of $15. These documents may be downloaded by selecting this project from the “Plan Room” link, and by entering Quest Project Number 7793278 on the “Browse Projects” page. For assistance and free membership registration, contact QuestCDN at 952.233.1632 or info@questcdn.com. For project inquiries, contact JHHarp@GarverUSA.com. Addendums to the bid package will be issued through the online Garver Plan Holders List; therefore, all prime bidders shall be responsible for downloading the bid documents from the Garver online plan room in order to be included in the Plan Holders List. Bidders must enter the addenda numbers in the Proposal to verify receipt.

Proposals shall be accompanied by a cashier's or certified check upon a national or state bank in an amount not less than five percent (5%) of the total maximum bid price payable without recourse to the Owner, or a bid bond in the same amount from a reliable surety company, as a guarantee that the Bidder will enter into a contract and execute performance and payment bonds within ten (10) days after notice of award of Contract to him. Such bid guarantee shall be made payable to City of Roanoke.

The successful bidder must furnish a performance and payment bond upon the form provided in the amount of one hundred per cent (100%) of the contract price from an approved surety company holding a permit from the State of Alabama to act as surety, or other surety or sureties acceptable to the Owner.

All Bidders shall make good faith efforts, as defined by Appendix A of 49 CFR Part 26, Regulations of the Office of the Secretary of Transportation, to subcontract a minimum of 7.76% of the dollar value of the prime contract to small business concerns owned and controlled by socially and economically disadvantaged individuals DBE).

Bidders must be licensed to perform work within the state of Alabama.

Federal Requirements for Federally Funded Projects. This Project is being partially funded under the Federal Aviation Administration (FAA) Airport Improvement Program (AIP). Contractors must comply with specific federally required provisions as listed herein and contained in the contract documents. The following federal provisions are incorporated in this solicitation by reference:

Buy American Preference (49 USC § 50101)

Trade Restriction Certification (49 USC § 50104, 49 CFR part 30)

Disadvantaged Business Enterprise (49 CFR part 26)

Davis-Bacon Requirements (2 CFR § 200, Appendix II(D), 29 CFR Part 5)

Procurement of Recovered Materials (2 CFR § 200.322, 40 CFR part 247, Solid Waste Disposal Act)

Debarment and Suspension (2 CFR part 180 (Subpart C), 2 CFR part 1200, DOT Order 4200.5)

Lobbying and Influencing Federal Employees (31 USC § 1352, 2 CFR part 200 Appendix II(J), 49 CFR part 20 Appendix A)

Affirmative Action Requirement.

1. The Bidder’s attention is called to the “Equal Opportunity Clause” and the “Standard Federal Equal Employment Opportunity Construction Contract Specifications” set forth herein.

2. The goals and timetables for minority and female participation, expressed in percentage terms for the Contractor’s aggregate workforce in each trade on all construction work in the covered area, are as follows:

Timetables

Goals for minority participation for each trade: 20.7%

Goals for female participation in each trade: 6.9%

These goals are applicable to all of the Contractor’s construction work (whether or not it is Federal or federally assisted) performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, it shall apply the goals established for such geographical area where the work is actually performed. With regard to this second area, the Contractor also is subject to the goals for both its federally involved and non-federally involved construction.

The Contractor’s compliance with the Executive Order and the regulations in 41 CFR Part 60-4 shall be based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations required by the specifications set forth in 41 CFR 60-4.3(a) and its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade, and the Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor or from project to project for the sole purpose of meeting the Contractor’s goals shall be a violation of the contract, the Executive Order and the regulations in 41 CFR Part 60-4. Compliance with the goals will be measured against the total work hours performed.

3. The Contractor shall provide written notification to the Director of the Office of Federal Contract Compliance Programs (OFCCP) within 10 working days of award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the name, address, and telephone number of the subcontractor; employer identification number of the subcontractor; estimated dollar amount of the subcontract; estimated starting and completion dates of the subcontract; and the geographical area in which the subcontract is to be performed.

4. As used in this notice and in the contract resulting from this solicitation, the “covered area” is Alabama, Randolph County, City of Roanoke.

Civil Rights Title VI Assurance

The City of Roanoke, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42 USC §§ 2000d to 2000d-4) and the Regulations, hereby notifies all Bidders that it will affirmatively ensure that any Contract entered into pursuant to this advertisement, disadvantaged business will be afforded full and fair opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.

The City of Roanoke reserves the right to reject any or all bids, to waive irregularities in the bids and bidding deemed to be in the best interests of Roanoke Municipal Airport, and to reject nonconforming, nonresponsive, or conditional bids.

Bids must remain in effect for 90 days after the bid opening date.

City of Roanoke

(17-19)

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.